Safe Routes To School Project

Location: Nolan River Road, Woodard Avenue and Colonial Drive

Project Information:  Installation of 28,820 l.f. (5.5 miles) of 5’ concrete sidewalks on Nolan River Road, Woodard Avenue and Colonial Drive.  The reconstruction of the City Hall parking lot. This includes concrete paving, benches and landscaping ($206,000)

Justification: To provide safer access and routes to schools for children. 

Project Start Date: June 19th, 2017

Estimate Completion Date:  May 2018 (320 calendar days)

Contractor: Westhill Construction, Inc.

Upcoming Closures/Detours:  To be announced

Approved Contract Value:  $1,551,115 (TxDOT funding of $779,969 – City $771,146)

Status: 25% complete.  Currently working on Nolan River Road.

Last Update: October 5, 2017      

Safe Routes To School Project