SR 174 North Sanitary Sewer Project

Location: US 67 - N. Lane Prairie Road

Project Information:  Installation of 26,723 l.f. (5.06 miles) of 8” – 24” sanitary sewer lines. The construction will begin at US 67 and will extend northward to Lane Prairie Road.

Justification: The reason behind this project is to provide sewer service to areas in the north city limits and encourage development.

Project Start Date: August 7, 2017

Estimate Completion Date:  April 2018 (210 calendar days)

Contractor: Venus Construction, Inc.

Upcoming Closures/Detours: To be announced 

Approved Contract Value:  $3,349,650

Status: 5% complete.  Working on clearing of work area.  Pipe installation will begin this week. 

Last Update: October 5, 2017