Cedar Street Drainage Project

Location: Cedar Street 

Project Information: Installation of a 60-inch diameter HP Storm pipe along Cedar Street extending from Wendell Street approximately 1,135 linear feet to the existing outlet head wall at the corner of Cedar and Blakney Streets. The road will be reconstructed with the project.

Justification: Due to the condition of the existing corrugated metal pipe and the likelihood of failure.

Project Start Date:  August 28, 2017

Estimated Completion Date:  January 2018 (150 calendar days)

Contractor: Reytech Services,  LLC

Upcoming Closures/Detours: To be announced

Approved Contract Value:  $493,512

Status:  30 % Complete – 600 ‘ of pipe has been installed.

Last Update: October 5, 2017