Yellow Jacket Sidewalk Project

Location: Yellow Jacket Drive

Project Information:  Installation of 2,500 linear feet of 5’ wide concrete sidewalk and drainage improvements along Yellow Jacket Drive from Harlin Drive to Nolan River Road.

Justification: To provide a continuous and safe pedestrian access to schools, churches, retail businesses, and residential neighborhoods along these roads.

Project Start Date: July 13th, 2017

Estimated Completion Date: Fall 2017

Engineer: Childress Engineering 

Upcoming Closures/Detours: To be announced 

Approved Contract Value: To be announced

Status:  Design is 90% complete.  City currently in the process of acquiring approximately 0.75 acres of right-of-way for the project.  The land is currently being appraised for acquisition.

Last Update: October 5, 2017