Sparks Drive Construction Project

Location: Sparks Drive

Project Information: 2,000 l.f. of paving (8” concrete), Bridge, Storm Sewer, and wetlands Mitigation

Justification: To be announced

Project Start Date: Fall 2016

Estimate Completion Date: Fall 2016

Engineer: Childress Engineering

Upcoming Closures/Detours: To be announced 

Estimate Cost:  $2,907,691

Status: The plans are 90% complete.  Approximately 60 days +/- away  from getting U.S. Corps of Engineers approval. Currently, working on an antiquities study for the Texas Historical Commission.  The plans can be completed approximately four weeks after U.S. Corps of Engineers approval of the wetlands mitigation plan.

Last Updated: October 5, 2017

sparks drive