City of Cleburne News

Posted on: August 23, 2017

Highway 174 North Sanitary Sewer Project

sewer

On June 27, 2017, City Council approved a bid from Venus Construction of Mansfield, Texas in the amount of $3,349,650.94 for the construction of the Highway 174 North Sanitary Sewer Project.

UPDATE: The reason behind this project is to provide sewer service to areas in the north city limits and encourage development.

The project will consist of the installation of approximately 22,000 linear feet of sanitary sewer line with pipe sizes ranging from 8” to 24”. The construction will begin at US 67 and will extend northward to Lane Prairie.

It is estimated that the project will take eight months to complete with a completion date of April 2018.

NMain_project2-page-001

Facebook Twitter Google Plus Email

Other News in City of Cleburne News

cedar stree

Cedar Street Project Update

Posted on: September 12, 2017
crossing guard

Be Mindful of Cross Guards

Posted on: September 8, 2017