- Home
- Living Here
- Public Works
- Public Works Construction Projects
- Wastewater Treatment Plant Expansion
Wastewater Treatment Plant Expansion
The City of Cleburne began the Wastewater Treatment Plant (WWTP) Expansion and Reuse Pump Station Project to address the increase in population and wastewater and water supply demand increases. As demand increases, so do the requirements set forth by the Texas Commission on Environmental Quality (TCEQ); this expansion will meet the TCEQ requirements as well. The $33-million dollar project has been in the works for years and finally broke ground in October of 2021. The expansion will increase the facilities average daily capacity and increase the peak flow capacity. The expanded WWTP will produce up to 2 MGD (million gallons per day) of high quality reclaimed effluent (treated and dechlorinated water) necessary for discharge into Lake Pat Cleburne as a means to augment the City's water supply. The proposed West Loop Reuse Pump Station will deliver the reclaimed effluent from the WWTP to Lake Pat Cleburne with an initial phase of 2 MGD of flow to the lake. The WWTP Expansion and Reuse Pump Station Project will include:
- An expansion to the influent pump station.
- A new flow control vault
- New headworks facility for the proposed treatment train
- New secondary treatment including aeration basins, blowers, return and waste activated sludge pumps and secondary clarifiers
- New tertiary media filters and UV disinfection for the new treatment train
- Rehabilitation of the existing chlorine contact basins and chlorine injection room
- Replace existing plant water pump station
- Expand the sludge dewatering building building
- Associated electrical controls and SCADA system improvements
- Associated yard piping and hydraulic improvements
- Drainage, landscaping and paving improvements
- New 2 MGD pump station
- New liquid sodium hypochlorite injection facilities
Engineer Design Firm
Freese & Nichols, Inc.
Contractor
Archer Western Construction, LLC.
Contact
For more information regarding the Wastewater Treatment Plant Expansion Project you may contact James Randell, City of Cleburne Utility Superintendent, at (817) 645-0946 or via Email. James Randell will be the City’s primary point of contact for this project and will be on site throughout the project.
Wastewater Treatment Plant Expansion Exhibit.
Timeline
Month | Progress |
---|---|
January 2023 |
Aeration Basin wall finishes were completed and the electrical was started. Installed SEC equipment in the Secondary Clarifiers. Subgrade and plumbing on the Sludge Pump Station. |
February 2023 |
Continued to poured walls for the UV Disinfection, erect canopy, installing UV equipment, slide gate and effluent weir. Continued laying piping for the plant drain, headworks influent and effluent. Installing raw sewage piping and underpaving. |
March 2023 |
Pending |
April 2023 |
Pending |
May 2023 |
Check back Mid-June for May 2023 updates. |
Timeline
Month |
Progress |
---|---|
January 2022 |
Contractors began laying new collection system piping and water line. They also began pouring the aeration basin foundation sections, walls, and roughing in the electrical. Excavation pipe laying began on the secondary clarifiers. |
February 2022 |
Work continued on the Aeration Basin Foundation. The Secondary Clarifier Excavation and North Influent Pump Station excavation continued. |
March 2022 |
Began laying new collection system piping and complete the water line. Continued with foundation pours and starting wall pours for the Aeration Basins. Continued excavation and laying pipes and foundation for the Secondary Clarifiers. |
April 2022 |
Continued with the new collection system piping, foundation pours, and the Aeration Basin. |
May 2022 |
Finished the foundation pours on the Aeration Basin, Secondary Clarifiers & Influent Pump Station. |
June 2022 |
Started the wall pours for Secondary Clarifiers, Aeration Basins & North Influent Pump Station. Started excavation and electrical rough in of the Electrical Building. |
July 2022 |
In SEC No. 4 started water leak testing, and SEC No. 3 and Aeration Basin continued with wall (95% complete) and walkway pours. |
August 2022 |
Continued laying the walkway pours for the Aeration Basins; finished the SW corner. North Influent Pump Station began valve pad work and prepared for installing pump and mixers. Starting excavation on the West Loop Pump Station. |
September 2022 |
Installing handrails, effluent troughs and beginning water tests for the Aeration Basins. Excavation and subgrade prep for Tertiary Filters, UV Disinfection & W Loop Pump Station. |
October 2022 |
Founded completed and masonry has started for the Electrical Building. Foundation and walls have started on the W Loop Pump Station & UV Disinfection. Headworks top deck concrete pour is complete. |
November 2022 |
The Secondary Clarifiers backfill is complete. West Loop Reuse Pump Station found and walls have started. Yard piping and site work has begun for the plant drain. WAS, headworks overflow to PFB. |
December 2022 |
Yard piping continues, Installing pumps and mixers at the North Influent Pump Station. Rough-in electrical & backfill the Aeration Basins. Site prepping the Tertiary Filters. West Loop Pump Station installing pump cans & water leak test. Fining demo of old drying beds. |
Timeline
Month |
Progress |
---|---|
October 5 2021 |
Groundbreaking Ceremony. |
November 2021 |
The Contractor has begun excavating of the new Aeration Basins. |
December 2021 |
Continued site prep work and excavating, contractor has begun laying new collection system piping. |